Table 38 : Implementation of Central Sector Projects - Status (end-March)

(Number of projects)
Sector/Year 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1. Atomic energy 4 1 3 4 6 6 6 5 5 5 4 3 5 4 4 4
a) Ahead 1 0 0 1 1 2 1 1 1 0 0 0 0 0 0 0
b) On Schedule 0 1 3 2 5 4 4 3 0 2 0 0 0 0 0 0
c) Delayed 3 0 0 1 0 0 1 1 4 3 3 2 4 3 4 4
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0
2. Civil aviation 0 0 0 0 0 1 1 1 2 3 18 8 5 6 8 7
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 0 0 0 0 1 0 0 2 1 4 2 1 2 2 0
c) Delayed 0 0 0 0 0 0 1 1 0 2 7 3 3 3 3 5
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 7 3 1 1 3 2
3. Coal 20 14 12 6 6 8 10 21 23 35 44 45 50 51 56 73
a) Ahead 0 0 0 0 0 0 0 0 0 1 4 0 0 0 0 0
b) On Schedule 5 6 9 3 4 7 9 20 21 26 16 25 31 22 24 33
c) Delayed 15 8 3 3 2 1 1 1 1 8 24 20 19 28 30 37
d) Without D.O.C. 0 0 0 0 0 0 0 0 1 0 0 0 0 1 2 3
4. Finance 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
c) Delayed 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5. Fertilisers 3 3 2 1 1 2 1 0 0 0 0 6 6 1 0 1
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 2 2 0 0 0 1 1 0 0 0 0 4 4 0 0 1
c) Delayed 0 0 1 1 1 1 0 0 0 0 0 1 2 1 0 0
d) Without D.O.C. 1 1 1 0 0 0 0 0 0 0 0 1 0 0 0 0
6. Mines 3 3 2 2 1 1 1 1 1 1 1 1 0 0 0 1
a) Ahead 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 1 2 1 1 0 1 1 1 1 0 0 0 0 0 0 1
c) Delayed 1 1 1 1 1 0 0 0 0 0 1 1 0 0 0 0
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0
7. Steel 3 1 1 2 3 7 9 12 21 28 29 13 16 17 20 25
a) Ahead 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 0 0 1 2 5 5 6 13 14 3 0 5 2 5 8
c) Delayed 3 1 1 1 1 1 4 6 7 14 20 7 10 15 13 17
d) Without D.O.C. 0 0 0 0 0 0 0 0 1 0 6 6 1 0 2 0
8. Petro-chemicals 1 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0
c) Delayed 1 0 0 0 0 0 0 0 0 0 0 0 0 1 0 1
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0
9. Petroleum 33 27 30 23 29 28 24 31 34 48 78 77 61 67 76 72
a) Ahead 2 3 2 3 4 4 1 1 4 3 5 6 1 0 1 2
b) On Schedule 14 19 22 10 13 11 9 5 9 19 29 29 17 20 17 19
c) Delayed 17 1 4 8 12 13 13 24 20 26 41 32 38 39 50 43
d) Without D.O.C. 0 4 2 2 0 0 1 1 1 0 3 10 5 8 8 8
(Continued)

TABLE 38 : IMPLEMENTATION OF CENTRAL SECTOR PROJECTS – STATUS
(End-March) (Concld.)
(Number of projects)
Sector 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
10. Power 25 25 32 35 41 44 56 57 57 62 77 81 101 101 96 105
a) Ahead 2 0 1 2 3 8 4 1 2 0 0 2 1 1 2 1
b) On Schedule 7 13 19 22 26 21 32 42 25 32 42 35 49 44 36 38
c) Delayed 15 11 12 11 12 15 20 12 28 28 33 43 50 53 44 63
d) Without D.O.C. 1 1 0 0 0 0 0 2 2 2 2 1 1 3 14 3
11. Railways 85 85 93 87 103 130 134 139 138 145 155 138 131 124 282 288
a) Ahead 2 2 1 0 0 0 0 1 0 1 5 2 2 0 0 0
b) On Schedule 7 5 6 5 6 5 7 4 4 10 11 23 25 8 15 11
c) Delayed 27 25 20 24 28 23 19 19 22 44 53 28 34 41 37 35
d) Without D.O.C. 49 53 66 58 69 102 108 115 112 90 86 85 70 75 230 242
12. Surface transport 21 22 12 100 90 71 122 190 204 186 174 145 157 168 151 140
a) Ahead 0 0 0 26 20 1 0 2 9 3 4 1 0 2 0 0
b) On Schedule 4 6 6 30 13 6 43 97 59 39 22 28 49 56 31 5
c) Delayed 17 16 6 44 53 62 65 82 131 139 143 114 93 95 23 104
d) Without D.O.C. 0 0 0 0 4 2 14 9 5 5 5 2 15 15 97 31
13. Telecommunication 2 2 0 1 2 25 28 31 26 34 40 41 16 13 10 4
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 1 0 1 1 3 2 0 0 6 0 1 0 0 0 1
c) Delayed 2 1 0 0 1 5 21 23 18 22 35 12 9 5 4 2
d) Without D.O.C. 0 0 0 0 0 17 5 8 8 6 5 28 7 8 6 1
14. Health & family welfare 0 2 2 2 2 2 2 1 1 1 1 0 0 0 0 0
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 0 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0
c) Delayed 0 0 0 0 0 2 2 1 0 0 0 0 0 0 0 0
d) Without D.O.C. 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0
15. Urban development 0 0 1 1 1 1 1 1 1 3 9 3 4 4 5 30
a) Ahead 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
b) On Schedule 0 0 0 0 0 0 0 1 1 2 1 0 2 2 2 6
c) Delayed 0 0 1 1 1 1 1 0 0 1 5 2 1 1 1 17
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 2 1 1 1 2 7
16. Others 1 1 0 0 1 1 1 1 1 1 1 1 1 1 1 0
a) Ahead 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) On Schedule 1 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0
c) Delayed 0 0 0 0 0 1 1 1 1 1 1 1 1 0 0 0
d) Without D.O.C. 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0
Total 202 187 190 264 286 327 396 491 514 552 631 562 554 558 710 751
a) Ahead 8 5 4 32 28 16 6 6 16 8 19 11 4 3 3 3
b) On Schedule 41 58 68 77 73 65 113 179 135 151 128 147 184 156 132 123
c) Delayed 102 65 49 95 112 125 149 171 232 288 366 266 264 285 209 328
d) Without D.O.C. 51 59 69 60 73 121 128 135 131 105 118 138 102 114 366 297
Notes :1. D.O.C. stands for Date of Commissioning.
2. For some delayed projects, information about the delay is not available, but they have date of commissioning.
3. Data relate to central sector projects costing ₹ 1 billion and above up to 2010. From 2011 onwards data pertain to projects costing ₹ 1.5 billion and above.
4. Delay is considered with reference to anticipated date of commissioning up to 2010. From 2011 onwards project is considered with reference to the original schedule of the projects..
Source : Ministry of Statistics and Programme Implementation, Government of India.

RbiTtsCommonUtility

प्ले हो रहा है
শুনি আছে

Related Assets

RBI-Install-RBI-Content-Global

RbiSocialMediaUtility

ভাৰতীয় ৰিজাৰ্ভ বেংক মোবাইল এপ্পলিকেষ্যন ইনষ্টল কৰক আৰু নৱীনতম বাতৰিৰ প্ৰৱেশাধিকাৰ পাওক!

Scan Your QR code to Install our app

RbiWasItHelpfulUtility

এই পৃষ্ঠাটো সহায়ক আছিল নে?