Table 36 : Sector-Wise Cost Overrun of Delayed Central Sector Projects - આરબીઆઈ - Reserve Bank of India
83800035
પ્રકાશિત તારીખ સપ્ટેમ્બર 15, 2019
Table 36 : Sector-Wise Cost Overrun of Delayed Central Sector Projects
(₹ Crores) | |||||||||||||||
Sector / Year | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
1. Atomic energy | |||||||||||||||
a) Number of projects | 0 | 0 | 1 | 1 | 3 | 3 | 3 | 3 | 4 | 3 | 4 | 4 | 4 | 4 | 4 |
b) Original estimate | 0 | 0 | 343 | 343 | 16586 | 20456 | 20876 | 17769 | 38056 | 36950 | 40442 | 40442 | 40442 | 40442 | 67120 |
c) Now anticipated | 0 | 0 | 343 | 343 | 16586 | 19525 | 22130 | 22607 | 40709 | 41049 | 46726 | 51918 | 51918 | 52241 | 69728 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | -931 | 1254 | 4838 | 2700 | 4100 | 6284 | 11476 | 11476 | 11799 | 2608 |
2. Civil aviation | |||||||||||||||
a) Number of projects | 0 | 0 | 1 | 1 | 0 | 2 | 7 | 3 | 3 | 3 | 3 | 5 | 1 | 3 | 1 |
b) Original estimate | 0 | 0 | 192 | 192 | 0 | 246 | 2823 | 2420 | 2588 | 2588 | 989 | 1659 | 309 | 842 | 315 |
c) Now anticipated | 0 | 0 | 192 | 192 | 0 | 246 | 2823 | 2420 | 2970 | 2970 | 1042 | 1712 | 309 | 1239 | 441 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 400 | 400 | 53 | 53 | 0 | 397 | 126 |
3. Coal | |||||||||||||||
a) Number of projects | 2 | 1 | 1 | 1 | 1 | 8 | 24 | 10 | 19 | 28 | 30 | 37 | 42 | 35 | 37 |
b) Original estimate | 384 | 200 | 200 | 200 | 287 | 6751 | 12689 | 5851 | 13791 | 24263 | 26241 | 28302 | 23987 | 19120 | 20254 |
c) Now anticipated | 569 | 183 | 183 | 183 | 287 | 8366 | 13962 | 7541 | 15102 | 26137 | 36435 | 32310 | 25308 | 19022 | 20473 |
d) Cost overrun | 185 | -17 | -17 | -17 | 0 | 1615 | 1273 | 1690 | 1300 | 1900 | 10194 | 4008 | 1322 | -98 | 219 |
4. Finance | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
b) Original estimate | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 |
c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
5. Fertilisers | |||||||||||||||
a) Number of projects | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 1 | 2 | 1 | 0 | 0 | 0 | 1 | 2 |
b) Original estimate | 350 | 350 | 0 | 0 | 0 | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 198 | 681 |
c) Now anticipated | 509 | 610 | 0 | 0 | 0 | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 209 | 693 |
d) Cost overrun | 159 | 260 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 | 12 |
6. Mines | |||||||||||||||
a) Number of projects | 1 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
b) Original estimate | 2062 | 0 | 0 | 0 | 0 | 0 | 4092 | 4092 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
c) Now anticipated | 2062 | 0 | 0 | 0 | 0 | 0 | 4092 | 4402 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 310 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 |
7. Steel | |||||||||||||||
a) Number of projects | 1 | 1 | 4 | 6 | 7 | 14 | 20 | 7 | 10 | 15 | 13 | 17 | 15 | 19 | 15 |
b) Original estimate | 299 | 107 | 773 | 1609 | 10268 | 22732 | 39430 | 30280 | 51099 | 64698 | 64208 | 56371 | 39095 | 41294 | 46113 |
c) Now anticipated | 299 | 170 | 773 | 1678 | 10273 | 27111 | 46120 | 39780 | 57158 | 70856 | 70162 | 59940 | 39601 | 41521 | 45901 |
d) Cost overrun | 0 | 63 | 0 | 69 | 5 | 4379 | 6690 | 9500 | 6100 | 6200 | 5954 | 3569 | 505 | 227 | -212 |
8. Petro-chemicals | |||||||||||||||
a) Number of projects | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 1 | 0 | 0 | 0 |
b) Original estimate | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5461 | 0 | 5461 | 0 | 0 | 0.00 |
c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 8920 | 0 | 9834 | 0 | 0 | 0.00 |
d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3500 | 0 | 4373 | 0 | 0 | 0.00 |
9. Petroleum | |||||||||||||||
a) Number of projects | 12 | 13 | 13 | 24 | 20 | 26 | 41 | 27 | 38 | 39 | 50 | 43 | 38 | 35 | 27 |
b) Original estimate | 13652 | 15982 | 24085 | 35560 | 29457 | 46429 | 86400 | 37562 | 107198 | 111743 | 139493 | 88533 | 47995 | 52021 | 52801 |
c) Now anticipated | 15010 | 19358 | 29692 | 45525 | 36871 | 56635 | 111051 | 40105 | 115427 | 121838 | 153759 | 101635 | 49999 | 52088 | 56325 |
d) Cost overrun | 1357 | 3376 | 5607 | 9965 | 7414 | 10206 | 24651 | 2542 | 8200 | 10100 | 14265 | 13102 | 2004 | 68 | 3524 |
(Continued) |
TABLE 36 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL SECTOR PROJECTS (End-March) (Concld.) |
|||||||||||||||
(₹ Crores) | |||||||||||||||
Sector / Year | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
10. Power | |||||||||||||||
a) Number of projects | 12 | 15 | 20 | 12 | 28 | 28 | 33 | 40 | 50 | 53 | 44 | 63 | 64 | 57 | 62 |
b) Original estimate | 7872 | 6963 | 18900 | 26973 | 52213 | 68600 | 82771 | 105569 | 137766 | 135656 | 124490 | 164942 | 171622 | 199226 | 227593 |
c) Now anticipated | 21545 | 16812 | 28220 | 27903 | 54332 | 72140 | 86254 | 110220 | 152267 | 150492 | 142172 | 193266 | 208830 | 230151 | 274184 |
d) Cost overrun | 13673 | 9849 | 9320 | 930 | 2119 | 3540 | 3483 | 4631 | 14500 | 14800 | 17681 | 28323 | 37208 | 30925 | 46591 |
11. Railways | |||||||||||||||
a) Number of projects | 28 | 23 | 19 | 19 | 22 | 44 | 53 | 31 | 34 | 41 | 37 | 35 | 31 | 38 | 29 |
b) Original estimate | 9282 | 8634 | 8992 | 8952 | 9758 | 15871 | 19388 | 22532 | 23671 | 27924 | 28589 | 29092 | 36714 | 41534 | 39411 |
c) Now anticipated | 14043 | 13612 | 17296 | 17823 | 21085 | 40072 | 40523 | 43774 | 56068 | 73537 | 73022 | 86253 | 90432 | 109806 | 110498 |
d) Cost overrun | 4760 | 4978 | 8305 | 8871 | 11327 | 24201 | 21135 | 21242 | 32400 | 45600 | 44432 | 57160 | 53718 | 68273 | 71087 |
12. Surface transport | |||||||||||||||
a) Number of projects | 53 | 62 | 65 | 82 | 131 | 139 | 143 | 109 | 93 | 95 | 23 | 104 | 128 | 107 | 48 |
b) Original estimate | 12584 | 16777 | 18244 | 22712 | 34972 | 40007 | 48532 | 39092 | 40272 | 54950 | 8843 | 77042 | 88402 | 85274 | 34465 |
c) Now anticipated | 13427 | 17045 | 18360 | 23404 | 35789 | 40643 | 48946 | 40490 | 43172 | 58195 | 11095 | 78983 | 90842 | 90139 | 36987 |
d) Cost overrun | 844 | 268 | 116 | 692 | 817 | 637 | 414 | 1399 | 2900 | 3250 | 2253 | 1941 | 2440 | 4865 | 2522 |
13. Telecommunication | |||||||||||||||
a) Number of projects | 1 | 5 | 21 | 23 | 18 | 22 | 35 | 35 | 9 | 5 | 4 | 2 | 2 | 2 | 2 |
b) Original estimate | 147 | 1601 | 6026 | 7978 | 7153 | 7513 | 14069 | 16628 | 3856 | 2935 | 2018 | 721 | 15445 | 15445 | 13752 |
c) Now anticipated | 147 | 1423 | 5563 | 7399 | 7177 | 6947 | 14391 | 17139 | 4035 | 2761 | 1843 | 721 | 15345 | 15345 | 25082 |
d) Cost overrun | 0 | -178 | -463 | -579 | 24 | -566 | 322 | 511 | 200 | -174 | -175 | 0 | -100 | -100 | 11330 |
14. Others | |||||||||||||||
a) Number of projects | 1 | 4 | 4 | 2 | 1 | 1 | 6 | 4 | 2 | 1 | 1 | 17 | 18 | 26 | 27 |
b) Original estimate | 4860 | 5544 | 5544 | 614 | 543 | 543 | 9111 | 15728 | 6938 | 6395 | 2494 | 82662 | 64808 | 98854 | 86365 |
c) Now anticipated | 10571 | 12332 | 12332 | 1492 | 1187 | 1187 | 10315 | 31872 | 12796 | 11609 | 2494 | 82662 | 72118 | 108617 | 87106 |
d) Cost overrun | 5711 | 6788 | 6788 | 878 | 644 | 644 | 1204 | 16144 | 5858 | 5214 | 0 | 0 | 7310 | 9763 | 741 |
Total | |||||||||||||||
a) Number of projects | 112 | 125 | 149 | 171 | 231 | 287 | 366 | 271 | 264 | 285 | 209 | 328 | 343 | 327 | 254 |
b) Original estimate | 51493 | 56159 | 83299 | 105133 | 161237 | 229148 | 340181 | 299002 | 425998 | 4750.42 | 437807 | 575227 | 528819 | 5942.48 | 588870 |
c) Now anticipated | 78182 | 81546 | 112954 | 125941 | 183587 | 272872 | 400607 | 361829 | 500467 | 5698.43 | 538750 | 699234 | 644702 | 720378 | 727418 |
d) Cost overrun | 26689 | 25388 | 29655 | 20808 | 22351 | 43724 | 60426 | 62827 | 74469 | 94801 | 100943 | 124007 | 115883 | 1261.30 | 138548 |
Notes : 1.Data relate to central sector projects costing ₹ 100 Crore and above up to 2010. From 2011 onwards data pertain to projects costing ₹ 150 Cr and above. 2.Projects without date of commissioning are not considered. 3.Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'. 4.Surface transport = Road transport + Shipping & ports. 5.Others = Heavy Industry+ Defence Production + Health & family welfare + Urban Development. Source : Ministry of Statistics and Programme Implementation, Government of India. |
प्ले हो रहा है
સાંભળો
શું આ પેજ ઉપયોગી હતું?