Page
Official Website of Reserve Bank of India
98489460
പ്രസിദ്ധീകരിച്ചത്
സെപ്റ്റംബർ 15, 2023
Table 36 : Sector-Wise Cost Overrun of Delayed Central Sector Projects
| (End-March) | |||||||||||||||
| (₹ Crore) | |||||||||||||||
| Sector / Year | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 1. Atomic energy | |||||||||||||||
| a) Number of projects | 3 | 3 | 3 | 4 | 3 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 3 | 3 |
| b) Original estimate | 20456 | 20876 | 17769 | 38056 | 36950 | 40442 | 40442 | 40442 | 40442 | 67120 | 67120 | 67120 | 67120 | 27271 | 27271 |
| c) Now anticipated | 19525 | 22130 | 22607 | 40709 | 41049 | 46726 | 51918 | 51918 | 52241 | 69728 | 75589 | 80348 | 80348 | 43139 | 43969 |
| d) Cost overrun | -931 | 1254 | 4838 | 2700 | 4100 | 6284 | 11476 | 11476 | 11799 | 2608 | 8469 | 13228 | 13228 | 15868 | 16698 |
| 2. Civil aviation | |||||||||||||||
| a) Number of projects | 2 | 7 | 3 | 3 | 3 | 3 | 5 | 1 | 3 | 1 | 1 | 4 | 11 | 4 | 6 |
| b) Original estimate | 246 | 2823 | 2420 | 2588 | 2588 | 989 | 1659 | 309 | 842 | 315 | 315 | 3235 | 8527 | 3288 | 3834 |
| c) Now anticipated | 246 | 2823 | 2420 | 2970 | 2970 | 1042 | 1712 | 309 | 1239 | 441 | 441 | 3362 | 8641 | 4358 | 6391 |
| d) Cost overrun | 0 | 0 | 0 | 400 | 400 | 53 | 53 | 0 | 397 | 127 | 127 | 127 | 114 | 1070 | 2556 |
| 3. Coal | |||||||||||||||
| a) Number of projects | 8 | 24 | 10 | 19 | 28 | 30 | 37 | 42 | 35 | 37 | 37 | 42 | 55 | 9 | 8 |
| b) Original estimate | 6751 | 12689 | 5851 | 13791 | 24263 | 26241 | 28302 | 23987 | 19120 | 20254 | 21142 | 23769 | 76470 | 28083 | 27219 |
| c) Now anticipated | 8366 | 13962 | 7541 | 15102 | 26137 | 36435 | 32310 | 25308 | 19022 | 20473 | 22274 | 29117 | 72521 | 33167 | 33110 |
| d) Cost overrun | 1615 | 1273 | 1690 | 1300 | 1900 | 10194 | 4008 | 1322 | -98 | 219 | 1133 | 5348 | -3949 | 5084 | 5890 |
| 4. Finance | |||||||||||||||
| a) Number of projects | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 1 |
| b) Original estimate | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 209 | 0 | 209 |
| c) Now anticipated | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 209 | 0 | 262 |
| d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 53 |
| 5. Fertilisers | |||||||||||||||
| a) Number of projects | 0 | 0 | 1 | 2 | 1 | 0 | 0 | 0 | 1 | 2 | 1 | 5 | 4 | 0 | 0 |
| b) Original estimate | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 198 | 681 | 198 | 1299 | 1101 | 0 | 0 |
| c) Now anticipated | 0 | 0 | 1479 | 763 | 1479 | 0 | 0 | 0 | 209 | 692 | 209 | 1311 | 1101 | 0 | 0 |
| d) Cost overrun | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 | 12 | 12 | 12 | 0 | 0 | 0 |
| 6. Mines | |||||||||||||||
| a) Number of projects | 0 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 3 | 3 | 3 |
| b) Original estimate | 0 | 4092 | 4092 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5707 | 6738 | 6429 | 4992 |
| c) Now anticipated | 0 | 4092 | 4402 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 5703 | 6738 | 7684 | 6303 |
| d) Cost overrun | 0 | 0 | 310 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | -3 | 0 | 1255 | 1311 |
| 7. Steel | |||||||||||||||
| a) Number of projects | 14 | 20 | 7 | 10 | 15 | 13 | 17 | 15 | 19 | 15 | 10 | 8 | 6 | 1 | 2 |
| b) Original estimate | 22732 | 39430 | 30280 | 51099 | 64698 | 64208 | 56371 | 39095 | 41294 | 46113 | 26774 | 25965 | 19922 | 15525 | 17618 |
| c) Now anticipated | 27111 | 46120 | 39780 | 57158 | 70856 | 70162 | 59940 | 39601 | 41521 | 45901 | 33578 | 33222 | 26337 | 21940 | 26062 |
| d) Cost overrun | 4379 | 6690 | 9500 | 6100 | 6200 | 5954 | 3569 | 505 | 227 | -213 | 6804 | 7257 | 6415 | 6415 | 8444 |
| 8. Petro-chemicals | |||||||||||||||
| a) Number of projects | 0 | 0 | 0 | 0 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| b) Original estimate | 0 | 0 | 0 | 0 | 5461 | 0 | 5461 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| c) Now anticipated | 0 | 0 | 0 | 0 | 8920 | 0 | 9834 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| d) Cost overrun | 0 | 0 | 0 | 0 | 3500 | 0 | 4373 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 9. Petroleum | |||||||||||||||
| a) Number of projects | 26 | 41 | 27 | 38 | 39 | 50 | 43 | 38 | 35 | 27 | 39 | 60 | 77 | 29 | 24 |
| b) Original estimate | 46429 | 86400 | 37562 | 107198 | 111743 | 139493 | 88533 | 47995 | 52021 | 52801 | 97368 | 144602 | 130932 | 66970 | 62453 |
| c) Now anticipated | 56635 | 111051 | 40105 | 115427 | 121838 | 153759 | 101635 | 49999 | 52088 | 56325 | 102310 | 156071 | 137876 | 91502 | 84502 |
| d) Cost overrun | 10206 | 24651 | 2542 | 8200 | 10100 | 14265 | 13102 | 2004 | 68 | 3524 | 4942 | 11470 | 6944 | 24532 | 22048 |
| (Continued) | |||||||||||||||
| TABLE 36 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL SECTOR PROJECTS (End-March) (Concld.) | |||||||||||||||
| (₹ Crore) | |||||||||||||||
| Sector / Year | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 10. Power | |||||||||||||||
| a) Number of projects | 28 | 33 | 40 | 50 | 53 | 44 | 63 | 64 | 57 | 62 | 51 | 47 | 51 | 27 | 22 |
| b) Original estimate | 68600 | 82771 | 105569 | 137766 | 135656 | 124490 | 164942 | 171622 | 199226 | 227593 | 199221 | 199760 | 222574 | 107459 | 78351 |
| c) Now anticipated | 72140 | 86254 | 110220 | 152267 | 150492 | 142172 | 193266 | 208830 | 230151 | 274184 | 244605 | 270014 | 291234 | 171791 | 134019 |
| d) Cost overrun | 3540 | 3483 | 4631 | 14500 | 14800 | 17681 | 28323 | 37208 | 30925 | 46590 | 45384 | 70254 | 68659 | 64332 | 55668 |
| 11. Railways | |||||||||||||||
| a) Number of projects | 44 | 53 | 31 | 34 | 41 | 37 | 35 | 31 | 38 | 29 | 97 | 149 | 157 | 158 | 131 |
| b) Original estimate | 15871 | 19388 | 22532 | 23671 | 27924 | 28589 | 29092 | 36714 | 41534 | 39411 | 123380 | 187725 | 201874 | 213625 | 194576 |
| c) Now anticipated | 40072 | 40523 | 43774 | 56068 | 73537 | 73022 | 86253 | 90432 | 109806 | 110498 | 201546 | 284516 | 323257 | 477384 | 455505 |
| d) Cost overrun | 24201 | 21135 | 21242 | 32400 | 45600 | 44432 | 57160 | 53718 | 68273 | 71087 | 78166 | 96791 | 121383 | 263759 | 260930 |
| 12. Surface transport | |||||||||||||||
| a) Number of projects | 139 | 143 | 109 | 93 | 95 | 23 | 104 | 128 | 107 | 48 | 111 | 188 | 155 | 154 | 119 |
| b) Original estimate | 40007 | 48532 | 39092 | 40272 | 54950 | 8843 | 77042 | 88402 | 85274 | 34466 | 96854 | 128612 | 85648 | 126843 | 79288 |
| c) Now anticipated | 40643 | 48946 | 40490 | 43172 | 58195 | 11095 | 78983 | 90842 | 90139 | 36987 | 99476 | 135951 | 88944 | 166366 | 101930 |
| d) Cost overrun | 637 | 414 | 1399 | 2900 | 3250 | 2253 | 1941 | 2440 | 4865 | 2522 | 2622 | 7339 | 3295 | 39523 | 22642 |
| 13. Telecommunication | |||||||||||||||
| a) Number of projects | 22 | 35 | 35 | 9 | 5 | 4 | 2 | 2 | 2 | 2 | 3 | 2 | 3 | 2 | 0 |
| b) Original estimate | 7513 | 14069 | 16628 | 3856 | 2935 | 2018 | 721 | 15445 | 15445 | 13752 | 13781 | 13566 | 14013 | 13765 | 0 |
| c) Now anticipated | 6947 | 14391 | 17139 | 4035 | 2761 | 1843 | 721 | 15345 | 15345 | 25082 | 25118 | 24904 | 25343 | 25125 | 0 |
| d) Cost overrun | -566 | 322 | 511 | 200 | -174 | -175 | 0 | -100 | -100 | 11330 | 11337 | 11338 | 11330 | 11360 | 0 |
| 14. Others | |||||||||||||||
| a) Number of projects | 1 | 6 | 4 | 2 | 1 | 1 | 17 | 18 | 26 | 27 | 27 | 56 | 69 | 35 | 35 |
| b) Original estimate | 543 | 9111 | 15728 | 6938 | 6395 | 2494 | 82662 | 64808 | 98854 | 86365 | 71272 | 129505 | 153112 | 152255 | 149433 |
| c) Now anticipated | 1187 | 10315 | 31872 | 12796 | 11609 | 2494 | 82662 | 72118 | 108617 | 87106 | 72514 | 177485 | 217166 | 223574 | 223853 |
| d) Cost overrun | 644 | 1204 | 16144 | 5858 | 5214 | 0 | 0 | 7310 | 9763 | 742 | 1242 | 47980 | 64054 | 71319 | 74422 |
| Total | |||||||||||||||
| a) Number of projects | 287 | 366 | 271 | 264 | 285 | 209 | 328 | 343 | 327 | 254 | 381 | 567 | 596 | 425 | 354 |
| b) Original estimate | 229148 | 340181 | 299002 | 425998 | 475042 | 437807 | 575227 | 528819 | 594248 | 588870 | 717425 | 930864 | 988240 | 761514 | 645244 |
| c) Now anticipated | 272872 | 400607 | 361829 | 500467 | 569843 | 538750 | 699234 | 644702 | 720378 | 727418 | 877661 | 1202005 | 1279714 | 1266030 | 1115907 |
| d) Cost overrun | 43724 | 60426 | 62827 | 74469 | 94801 | 100943 | 124007 | 115883 | 126130 | 138548 | 160236 | 271140 | 291474 | 504516 | 470663 |
| Notes : 1. Data relate to central sector projects costing ₹100 Crore and above up to 2010. From 2011 onwards data pertain to projects costing ₹150 Crore and above. 2. Projects without date of commissioning are not considered. 3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'. 4. Surface transport = Road transport + Shipping & ports. 5. Others = Heavy Industry+ Defence Production + Health & family welfare + Urban Development. Source : Ministry of Statistics and Programme Implementation, Government of India. |
|||||||||||||||
प्ले हो रहा है
കേൾക്കുക
പേജ് അവസാനം അപ്ഡേറ്റ് ചെയ്തത്:
ഈ പേജ് സഹായകരമായിരുന്നോ?