Table 38 : Sector-Wise Cost Overrun of Delayed Central Sector Projects (end-March)

(Rupees crore)

Sector / Year

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

1. Atomic energy

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

5

5

3

3

0

0

1

0

0

1

1

3

3

3

b) Original estimate

2439.3

2455.6

1937.8

1937.8

0.0

0.0

3447.1

0.0

0.0

343.3

343.3

16586.3

20456.0

20876.0

c) Now anticipated

4904.0

5041.3

5713.7

5713.7

0.0

0.0

6760.0

0.0

0.0

343.3

343.3

16586.3

19525.0

22130.0

d) Cost overrun

2464.6

2585.7

3775.9

3775.9

0.0

0.0

3312.9

0.0

0.0

0.0

0.0

0.0

-931.0

1254.0

2. Civil aviation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

3

2

2

0

0

0

0

0

0

1

1

0

2

7

b) Original estimate

1431.8

294.1

294.1

0.0

0.0

0.0

0.0

0.0

0.0

191.5

191.5

0.0

245.6

2822.8

c) Now anticipated

1703.9

566.2

566.2

0.0

0.0

0.0

0.0

0.0

0.0

191.5

191.5

0.0

245.6

2822.8

d) Cost overrun

272.1

272.1

272.1

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

3. Coal

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

13

15

16

15

8

3

3

2

1

1

1

1

8

24

b) Original estimate

4060.1

6279.9

8320.8

7191.9

5356.2

1975.0

1975.0

384.4

199.9

199.9

199.9

287.2

6750.9

12689.3

c) Now anticipated

6207.5

7722.7

9925.1

8686.2

6348.2

2010.3

1992.5

569.0

182.6

182.6

182.6

287.2

8366.2

13962.3

d) Cost overrun

2147.4

1442.8

1604.3

1494.3

992.0

35.3

17.5

184.6

-17.3

-17.3

-17.3

0.0

1615.3

1273.0

4. Finance

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

1

1

1

1

1

0

0

0

0

0

0

0

0

0

b) Original estimate

118.3

118.3

118.3

118.3

118.3

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

c) Now anticipated

348.8

348.8

348.8

348.8

301.8

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

d) Cost overrun

230.5

230.5

230.5

230.5

183.5

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

5. Fertilisers

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

3

1

0

0

0

1

1

1

1

0

0

0

0

0

b) Original estimate

2093.2

618.4

0.0

0.0

0.0

350.0

350.0

350.0

350.0

0.0

0.0

0.0

0.0

0.0

c) Now anticipated

2195.4

642.4

0.0

0.0

0.0

509.4

509.4

509.4

610.2

0.0

0.0

0.0

0.0

0.0

d) Cost overrun

102.2

23.9

0.0

0.0

0.0

159.4

159.4

159.4

260.2

0.0

0.0

0.0

0.0

0.0

6. Mines

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

0

0

0

1

1

1

1

1

0

0

0

0

0

1

b) Original estimate

0.0

0.0

0.0

157.5

157.5

2062.0

2062.0

2062.0

0.0

0.0

0.0

0.0

0.0

4091.5

c) Now anticipated

0.0

0.0

0.0

157.5

183.6

2062.0

2062.0

2062.0

0.0

0.0

0.0

0.0

0.0

4091.5

d) Cost overrun

0.0

0.0

0.0

0.0

26.1

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

7. Steel

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

3

5

4

3

1

1

1

1

1

4

6

7

14

20

b) Original estimate

5443.8

6511.1

5154.1

2693.1

430.5

430.5

298.7

298.7

107.4

773.3

1609.1

10268.4

22731.8

39430.4

c) Now anticipated

11167.9

13498.8

8856.7

3787.7

466.7

450.0

298.7

298.7

170.4

773.3

1677.7

10273.0

27110.6

46120.2

d) Cost overrun

5724.2

6987.7

3702.6

1094.6

36.2

19.5

0.0

0.0

63.0

0.0

68.6

4.6

4378.8

6689.8

8. Petro-chemicals

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

3

3

1

1

0

0

0

0

0

0

0

0

0

0

b) Original estimate

3820.7

3820.7

3484.4

3484.4

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

c) Now anticipated

3841.4

3852.6

3809.0

3809.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

d) Cost overrun

20.6

31.8

324.6

324.6

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

9. Petroleum

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

13

17

22

17

1

4

8

12

13

13

24

20

26

41

b) Original estimate

16602.1

18890.6

20238.6

15905.4

133.6

2702.7

9948.3

13652.3

15982.2

24085.3

35560.1

29456.8

46428.6

86400.0

c) Now anticipated

18169.4

20715.9

22058.1

16899.1

118.1

2624.7

11030.1

15009.7

19358.4

29692.2

45525.1

36871.1

56634.5

11051.0

d) Cost overrun

1567.4

1825.3

1819.5

993.7

-15.5

-78.0

1081.8

1357.4

3376.2

5606.9

9965.0

7414.2

10205.9

24651.0

(Continued)


TABLE 38 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL SECTOR PROJECTS (End-March) (Concld.)

(Rupees crore)

Sector/Year

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

10. Power

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

22

20

19

15

11

12

11

12

15

20

12

28

28

33

b) Original estimate

14459.6

9710.0

10233.3

9143.9

8670.5

11445.9

9985.1

7872.3

6963.4

18900.0

26973.1

52212.9

68599.9

82770.5

c) Now anticipated

32023.3

22552.1

23456.5

24646.3

22920.6

28176.9

24005.8

21545.4

16812.2

28220.0

27902.7

54332.0

72140.2

86253.8

d) Cost overrun

17563.7

12842.1

13223.2

15502.4

14250.1

16731.0

14020.7

13673.1

9848.8

9320.0

929.6

2119.1

3540.3

3483.3

11. Railways

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

37

20

27

27

25

20

24

28

23

19

19

22

44

53

b) Original estimate

5380.5

3726.1

5254.8

7909.8

7038.9

6690.1

8036.4

9282.4

8634.2

8991.5

8952.0

9757.5

15870.9

19388.2

c) Now anticipated

11429.6

6322.8

8443.8

12431.6

12171.8

10336.9

12472.1

14042.8

13612.3

17296.3

17823.3

21084.8

40071.8

40523.2

d) Cost overrun

6049.0

2596.8

3189.0

4521.8

5132.9

3646.8

4435.7

4760.4

4978.2

8304.8

8871.3

11327.4

24200.9

21134.9

12. Surface transport

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

16

20

18

17

16

6

44

53

62

65

82

131

139

143

b) Original estimate

2990.4

3666.2

3256.9

3326.4

3078.8

898.3

10656.5

12583.9

16777.2

18243.8

22712.1

34971.7

40006.5

48532.2

c) Now anticipated

3864.2

5362.0

5216.6

5290.5

5847.7

1809.8

11362.9

13427.4

17044.9

18359.7

23403.6

35788.6

40640.4

48946.3

d) Cost overrun

873.7

1695.9

1959.8

1964.1

2768.9

911.5

706.4

843.5

267.7

115.9

691.5

816.9

633.9

414.1

13.Telecomm
unication

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

0

2

0

2

1

0

0

1

5

21

23

18

22

35

b) Original estimate

0.0

465.6

0.0

730.8

546.0

0.0

0.0

147.0

1600.5

6026.2

7977.8

7152.9

7512.7

14068.5

c) Now anticipated

0.0

671.9

0.0

730.8

546.0

0.0

0.0

147.0

1422.9

5562.8

7398.7

7177.4

6946.5

14390.9

d) Cost overrun

0.0

206.3

0.0

0.0

0.0

0.0

0.0

0.0

-177.6

-463.4

-579.1

24.4

-566.1

322.4

14. Others

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

0

0

0

0

0

1

1

1

4

4

2

2

1

6

b) Original estimate

0.0

0.0

0.0

0.0

0.0

4860.0

4860.0

4860.0

5543.8

5543.8

614.1

8660.9

542.9

9110.6

c) Now anticipated

0.0

0.0

0.0

0.0

0.0

8800.0

8800.0

10571.0

12332.2

12332.2

1492.0

9863.0

1187.0

10314.7

d) Cost overrun

0.0

0.0

0.0

0.0

0.0

3940.0

3940.0

5711.0

6788.4

6788.4

877.9

1202.1

644.1

1204.1

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

a) Number of projects

119

111

113

102

65

49

95

112

125

149

171

232

287

366

b) Original estimate

58839.8

56556.6

58293.1

52599.3

25530.3

31414.5

51619.1

51493.0

56158.6

83298.6

105133.0

169354.6

229145.8

340180.0

c) Now anticipated

95855.4

87297.5

88394.5

82501.2

48904.5

56780.0

79293.5

78182.4

81546.1

112953.9

125940.5

192263.4

272867.8

400606.7

d) Cost overrun

37015.4

30740.9

30101.5

29901.9

23374.2

25365.5

27674.4

26689.4

25387.6

29655.3

20807.5

22908.7

43722.1

60426.6

Note : 1. Data relate to central sector projects costing Rupees 100 crore and above.
2. Projects without date of commissioning are not considered.
3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'.
Source : Ministry of Statistics and Programme Implementation, Government of India.

RbiTtsCommonUtility

प्ले हो रहा है
കേൾക്കുക

Related Assets

RBI-Install-RBI-Content-Global

RbiSocialMediaUtility

റിസർവ് ബാങ്ക് ഓഫ് ഇന്ത്യ മൊബൈൽ ആപ്ലിക്കേഷൻ ഇൻസ്റ്റാൾ ചെയ്ത് ഏറ്റവും പുതിയ വാർത്തകളിലേക്ക് വേഗത്തിലുള്ള ആക്സസ് നേടുക!

Scan Your QR code to Install our app

RbiWasItHelpfulUtility

ഈ പേജ് സഹായകരമായിരുന്നോ?