Design, Supply, Installation, Testing and Commissioning of 50 KWp Roof Top Grid Interactive SPV based Solar Power System for Bank's Residential Quarters (Nayapalli) at Bhubaneswar
Tender number | RBI/Bhubaneswar Regional Office/Estate/9/25-26/ET/221 |
Date of publication of NIT | ஜூன் 24, 2025 from 18:00 Hrs. |
Nature of work | Design, Supply, Installation, Testing and Commissioning of 50 KWp Roof Top Grid Interactive SPV based Solar Power System for Bank's Residential Quarters (Nayapalli) at Bhubaneswar |
Mode of tender enquiry | e-Tender on MSTC website |
Type of bidding (single/two bid system) | Two Bid system |
Last date of receipt of tender | ஜூலை 21, 2025 up to 14:00 hrs |
Number of tenders received | 06 (Six) 1. M/s Nemhans Solutions Pvt. Ltd. 2. M/s Power One Micro Systems Pvt. Ltd. 3. M/s Greenco Systems Pvt. Ltd. 4. M/s Parklands Solar Pvt. Ltd. 5. M/s Alfa Projects & Services Pvt ltd 6. M/s Agni Green Power Limited |
Nos. and names of parties qualified after technical evaluation | 05 (Five) 1. M/s Nemhans Solutions Pvt. Ltd. 2. M/s Power One Micro Systems Pvt. Ltd. 3. M/s Greenco Systems Pvt. Ltd. 4. M/s Alfa Projects & Services Pvt ltd 5. M/s Agni Green Power Limited |
Nos. and names of parties not qualified after technical evaluation | 01 (One) M/s Parklands Solar Pvt. Ltd. |
Commercial Bid Ranking, if any | - |
Final Ranking, if any | - |
Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
Contract number and date | BBS.ESTT.ESAD.No.S398/03-03-022/2025-2026 dated August 14, 2025 |
Name of contractor | M/s Power-One Micro Systems (P) Ltd. |
Value of contract | Capital cost - ₹23,00,000.00 CAMC - ₹23,000.00 per annum |
Scheduled date of completion of supplies | within 12 weeks from the 14th day of issue of issue of the work order |
Actual date of start of work | Shall be shared after completion of the work |
Actual date of completion of work | Shall be shared after completion of the work |
Reasons for delay, if any | Shall be shared after completion of the work |