Supply, Installation, Testing and Commissioning of 32 no. of Split Acs (1.5TR) at the Reserve Bank Staff College, Chennai
Supply, Installation, Testing and Commissioning of 32 no. of Split Acs (1.5TR) at the Reserve Bank Staff College, Chennai
| Tender number | RBI/Reserve Bank Staff College/Estate/7/25-26/ET/673 |
| Date of publication of NIT | دسمبر , 12 2025 |
| Nature of work | Supply, Installation, Testing and Commissioning of 32 no. of Split Acs (1.5TR) at the Reserve Bank Staff College, Chennai |
| Mode of tender enquiry | E-Tender |
| Type of bidding (single/two bid system) | Two Bid |
| Last date of receipt of tender | جنوری , 02 2026 |
| Number of tenders received | 01 (One) |
| Nos. and names of parties qualified after technical evaluation | 01 (One) i. Gem Cooling Engineering |
| Nos. and names of parties not qualified after technical evaluation | NIL |
| Commercial Bid Ranking, if any | - |
| Final Ranking, if any | - |
| Contract number and date | RBSC.ESTT.ESAD.No.S-120/02.06.027 / 2025-26 dated جنوری , 14 2026 |
| Name of contractor | M/s. Gem Cooling Engineering |
| Value of contract | ₹ 25,08,788 /- |
| Scheduled date of completion of supplies | Within 45 days from the 10th day of issue of work order |
| Actual date of start of work | - |
| Actual date of completion of work | - |
| Reasons for delay, if any | - |
Data Releases
This Section provides data on various aspects of Indian economy, banking and finance. While the current data defined as data for the past one year is available at the links provided below, researchers may also access data series available in the Database on Indian Economy link available on this page.