External texture painting, cleaning of lift wells, supply of curtain rods and other works at Centre For Advanced Financial Research And Learning (CAFRAL) at Dadar (West) Mumbai
| Tender number | RBI/Mumbai Regional Office/Estate/102/25 26/ET/617 |
| Date of publication of NIT | Dec 22, 2025 |
| Nature of work | External texture painting, cleaning of lift wells, supply of curtain rods and other works at Centre For Advanced Financial Research And Learning (CAFRAL) at Dadar (West) Mumbai |
| Mode of tender enquiry | MSTC |
| Type of bidding (single/two bid system) | Two bid system |
| Last date of receipt of tender | Jan 01, 2026 |
| Number of tenders received | 05(Five) |
| Nos. and names of parties qualified after technical evaluation | 05(Five) 1.M/s Shivam Enterprises 2.M/s Bombay Construction 3.M/s Raj Enterprises 4.M/s G.S. Interior 5.M/s Aakar Shilp |
| Nos. and names of parties not qualified after technical evaluation | NIL |
| Commercial Bid Ranking, if any | 1.M/s G.S. Interior 2.M/s Aakar Shilp 3.M/s Shivam Enterprises 4.M/s Raj Enterprises 5.M/s Bombay Construction |
| Final Ranking, if any | 1.M/s G.S. Interior 2.M/s Aakar Shilp 3.M/s Shivam Enterprises 4.M/s Raj Enterprises 5.M/s Bombay Construction |
| Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
| Contract number and date | MRO.ESTT.ECFRL.No.S2062/09-01-001/2025-2026 dated Jan 20, 2026 |
| Name of contractor | M/s G.S. Interior |
| Value of contract | ₹ 22,68,668/- |
| Scheduled date of completion of supplies | One month which shall be reckoned from the 10th day of work order or handing over of the site for commencement of the work whichever is later. |
| Actual date of start of work | - |
| Actual date of completion of work | - |
| Reasons for delay, if any | - |