Table 39 : Sector-Wise Cost Overrun of Delayed Central Sector Projects (end-March)

(₹ Billion)
Sector / Year 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1. Atomic energy                              
a) Number of projects 0 0 1 0 0 1 1 3 3 3 3 4 3 4 4
b) Original estimate 0.00 0.00 34.47 0.00 0.00 3.43 3.43 165.86 204.56 208.76 177.69 380.56 369.50 404.42 404.42
c) Now anticipated 0.00 0.00 67.60 0.00 0.00 3.43 3.43 165.86 195.25 221.30 226.07 407.09 410.49 467.26 519.18
d) Cost overrun 0.00 0.00 33.13 0.00 0.00 0.00 0.00 0.00 -9.31 12.54 48.38 27.00 41.00 62.84 114.76
2. Civil aviation                              
a) Number of projects 0 0 0 0 0 1 1 0 2 7 3 3 3 3 5
b) Original estimate 0.00 0.00 0.00 0.00 0.00 1.92 1.92 0.00 2.46 28.23 24.20 25.88 25.88 9.89 16.59
c) Now anticipated 0.00 0.00 0.00 0.00 0.00 1.92 1.92 0.00 2.46 28.23 24.20 29.70 29.70 10.42 17.12
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 4.00 0.53 0.53
3. Coal                              
a) Number of projects 8 3 3 2 1 1 1 1 8 24 10 19 28 30 37
b) Original estimate 53.56 19.75 19.75 3.84 2.00 2.00 2.00 2.87 67.51 126.89 58.51 137.91 242.63 262.41 283.02
c) Now anticipated 63.48 20.10 19.93 5.69 1.83 1.83 1.83 2.87 83.66 139.62 75.41 151.02 261.37 364.35 323.10
d) Cost overrun 9.92 0.35 0.18 1.85 -0.17 -0.17 -0.17 0.00 16.15 12.73 16.90 13.00 19.00 101.94 40.08
4. Finance                              
a) Number of projects 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
b) Original estimate 1.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
c) Now anticipated 3.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d) Cost overrun 1.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5. Fertilisers                              
a) Number of projects 0 1 1 1 1 0 0 0 0 0 1 2 1 0 0
b) Original estimate 0.00 3.50 3.50 3.50 3.50 0.00 0.00 0.00 0.00 0.00 14.79 7.63 14.79 0.00 0.00
c) Now anticipated 0.00 5.09 5.09 5.09 6.10 0.00 0.00 0.00 0.00 0.00 14.79 7.63 14.79 0.00 0.00
d) Cost overrun 0.00 1.59 1.59 1.59 2.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6. Mines                              
a) Number of projects 1 1 1 1 0 0 0 0 0 1 1 0 0 0 0
b) Original estimate 1.58 20.62 20.62 20.62 0.00 0.00 0.00 0.00 0.00 40.92 40.92 0.00 0.00 0.00 0.00
c) Now anticipated 1.84 20.62 20.62 20.62 0.00 0.00 0.00 0.00 0.00 40.92 44.02 0.00 0.00 0.00 0.00
d) Cost overrun 0.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.10 0.00 0.00 0.00 0.00
7. Steel                              
a) Number of projects 1 1 1 1 1 4 6 7 14 20 7 10 15 13 17
b) Original estimate 4.31 4.31 2.99 2.99 1.07 7.73 16.09 102.68 227.32 394.30 302.80 510.99 646.98 642.08 563.71
c) Now anticipated 4.67 4.50 2.99 2.99 1.70 7.73 16.78 102.73 271.11 461.20 397.80 571.58 708.56 701.62 599.40
d) Cost overrun 0.36 0.20 0.00 0.00 0.63 0.00 0.69 0.05 43.79 66.90 95.00 61.00 62.00 59.54 35.69
8. Petro-chemicals                              
a) Number of projects 0 0 0 0 0 0 0 0 0 0 0 0 1 0 1
b) Original estimate 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.61 0.00 54.61
c) Now anticipated 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 89.20 0.00 98.34
d) Cost overrun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.00 0.00 43.73
9. Petroleum                              
a) Number of projects 1 4 8 12 13 13 24 20 26 41 27 38 39 50 43
b) Original estimate 1.34 27.03 99.48 136.52 159.82 240.85 355.60 294.57 464.29 864.00 375.62 1071.98 1117.43 1394.93 885.33
c) Now anticipated 1.18 26.25 110.30 150.10 193.58 296.92 455.25 368.71 566.35 1110.51 401.05 1154.27 1218.38 1537.59 1016.35
d) Cost overrun -0.16 -0.78 10.82 13.57 33.76 56.07 99.65 74.14 102.06 246.51 25.42 82.00 101.00 142.65 131.02
(Continued)

TABLE 39 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL
SECTOR PROJECTS (End-March) (Concld.)
(₹ Billion)
Sector / Year 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
10. Power                              
a) Number of projects 11 12 11 12 15 20 12 28 28 33 40 50 53 44 63
b) Original estimate 86.71 114.46 99.85 78.72 69.63 189.00 269.73 522.13 686.00 827.71 1055.69 1377.66 1356.56 1244.90 1649.42
c) Now anticipated 229.21 281.77 240.06 215.45 168.12 282.20 279.03 543.32 721.40 862.54 1102.20 1522.67 1504.92 1421.72 1932.66
d) Cost overrun 142.50 167.31 140.21 136.73 98.49 93.20 9.30 21.19 35.40 34.83 46.31 145.00 148.00 176.81 283.23
11. Railways                              
a) Number of projects 25 20 24 28 23 19 19 22 44 53 31 34 41 37 35
b) Original estimate 70.39 66.90 80.36 92.82 86.34 89.92 89.52 97.58 158.71 193.88 225.32 236.71 279.24 285.89 290.92
c) Now anticipated 121.72 103.37 124.72 140.43 136.12 172.96 178.23 210.85 400.72 405.23 437.74 560.68 735.37 730.22 862.53
d) Cost overrun 51.33 36.47 44.36 47.60 49.78 83.05 88.71 113.27 242.01 211.35 212.42 324.00 456.00 444.32 571.60
12. Surface transport                              
a) Number of projects 16 6 44 53 62 65 82 131 139 143 109 93 95 23 104
b) Original estimate 30.79 8.98 106.57 125.84 167.77 182.44 227.12 349.72 400.07 485.32 390.92 402.72 549.50 88.43 770.42
c) Now anticipated 58.48 18.10 113.63 134.27 170.45 183.60 234.04 357.89 406.43 489.46 404.90 431.72 581.95 110.95 789.83
d) Cost overrun 27.69 9.12 7.06 8.44 2.68 1.16 6.92 8.17 6.37 4.14 13.99 29.00 32.50 22.53 19.41
13. Telecommunication                              
a) Number of projects 1 0 0 1 5 21 23 18 22 35 35 9 5 4 2
b) Original estimate 5.46 0.00 0.00 1.47 16.01 60.26 79.78 71.53 75.13 140.69 166.28 38.56 29.35 20.18 7.21
c) Now anticipated 5.46 0.00 0.00 1.47 14.23 55.63 73.99 71.77 69.47 143.91 171.39 40.35 27.61 18.43 7.21
d) Cost overrun 0.00 0.00 0.00 0.00 -1.78 -4.63 -5.79 0.24 -5.66 3.22 5.11 2.00 -1.74 -1.75 0.00
14. Others                              
a) Number of projects 0 1 1 1 4 4 2 1 1 6 4 2 1 1 17
b) Original estimate 0.00 48.60 48.60 48.60 55.44 55.44 6.14 5.43 5.43 91.11 157.28 69.38 63.95 24.94 826.62
c) Now anticipated 0.00 88.00 88.00 105.71 123.32 123.32 14.92 11.87 11.87 103.15 318.72 127.96 116.09 24.94 826.62
d) Cost overrun 0.00 39.40 39.40 57.11 67.88 67.88 8.78 6.44 6.44 12.04 161.44 58.58 52.14 0.00 0.00
Total                              
a) Number of projects 65 49 95 112 125 149 171 231 287 366 271 264 285 209 328
b) Original estimate 255.30 314.15 516.19 514.93 561.59 832.99 1051.33 1612.37 2291.48 3401.81 2990.02 4259.98 4750.42 4378.08 5752.27
c) Now anticipated 489.05 567.80 792.94 781.82 815.46 1129.54 1259.41 1835.87 2728.72 4006.07 3618.29 5004.67 5698.43 5387.49 6992.33
d) Cost overrun 233.74 253.66 276.74 266.89 253.88 296.55 208.08 223.51 437.24 604.26 628.27 745.58 948.90 1009.40 1240.07
Notes : 1. Data relate to central sector projects costing ₹ 1 billion and above up to 2010. From 2011 onwards data pertain to projects costing ₹ 1.5 billion and above.
2. Projects without date of commissioning are not considered.
3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'.
Source : Ministry of Statistics and Programme Implementation, Government of India.

RbiTtsCommonUtility

प्ले हो रहा है
వినండి

Related Assets

RBI-Install-RBI-Content-Global

RbiSocialMediaUtility

భారతీయ రిజర్వ్ బ్యాంక్ మొబైల్ అప్లికేషన్‌ను ఇన్‌స్టాల్ చేయండి మరియు తాజా వార్తలకు త్వరిత యాక్సెస్ పొందండి!

Scan Your QR code to Install our app

RbiWasItHelpfulUtility

ఈ పేజీ ఉపయోగకరంగా ఉందా?